Southworth Construction

Southworth Construction Timeline
  •  Project Tasks Anticipated Completion
    Survey May 2019 - Complete
    GeoTech Report April 2019 - Complete
    Transportation Study April 2019 - Complete
    Conceptual Site Plan May 2019 - Complete
    Educational Specifications October 2019 - Complete
    Schematic Design Approval December 2019 - Complete
    Design Development May - September 2020 - Complete
    Bidding January - April 2021 - Complete
    Move SW to old YMS building June 2021 - Complete
    Construction Begins June 2021 - In Progress
    Substantial Completion July 2022

Project Information

  • The Community Facilities Advisory Committee recommendations included a replacement middle school to help accommodate the district’s growing enrollment, aging school and safety of campus design.

    Architect: Heather Hocklander, BCRA Lead Manager 
    Construction Manager:  Kasey Wyatt, KWA
    Contractor: FORMA Construction
    Square Footage: 65,000 sq ft
    Capacity: 550 students
    Instructional Spaces: classrooms, instrumental and vocal music, special education, art, library, cafeteria/commons with stage, and gymnasium
    Estimated Project Cost: $43,428,000
    Planned opening: September 2022

    Questions/Concerns about job site, please contact

    FORMA
    PO Box 11489
    Olympia, WA 98508
    360-754-5788
    360-943-5868
    info@formacc.com

Last Modified on November 10, 2021