Southworth Construction Timeline
  •  Project Tasks Anticipated Completion
    Survey May 2019 - Complete
    GeoTech Report April 2019 - Complete
    Transportation Study April 2019 - Complete
    Conceptual Site Plan May 2019 - Complete
    Educational Specifications October 2019 - Complete
    Schematic Design Approval December 2019 -Complete
    Design Development May - September 2020
    Bidding January - April 2021
    Move SW to old YMS building June 2021
    Construction Begins June 2021
    Substantial Completion July 2022
  • Southworth Elementary
    Project Information

    The Community Facilities Advisory Committee recommendations included a replacement middle school to help accommodate the district’s growing enrollment, aging school and safety of campus design.

    Architect: Heather Hocklander, BCRA Lead Manager 
    Construction Manager:  Kasey Wyatt, KWA
    Contractor: FORMA Construction
    Square Footage: 65,000 sq ft
    Capacity: 550 students
    Instructional Spaces: classrooms, instrumental and vocal music, special education, art, library, cafeteria/commons with stage, and gymnasium
    Estimated Project Cost: $43,428,000
    Planned opening: September 2022